Decks 93 Howard
Another
great re-deck but this one came with a big surprise. Once the decking came
off we found not one post in the ground. The deck
was
supported by cinder blocks only. The deck frame moved considerably while
floating on the topsoil causing huge deck board problems.
We
re-framed the deck to eliminate a cutout in the original layout, sunk over
36 posts in concrete, then re-decked and stained. The
project
was completed with three benches in 5 days time.